IRM ROLLING SCHEDULE

Rolling Schedule

Rolling dates are approximate and indicate the planned end of rolling. Delivery could be up to two weeks after the actual rolling.

  • 4.75 mm requires minimum of 350 tons to justify rolling.
  • Rebar requires minimum of 600 tons to justify rolling
  • All other diameters require minimum of 280 tons.

4.75 mm .1875 " 3/16

Oct 2843E
Nov 2647E
Dec 1551E
Jan 1502E

5.50 mm .216 " 7/32

Oct 2743D
Nov 2647D
Dec 1551D
Jan 1502D

6.00 mm .234 " 15/64

Oct 2443C
Nov 2147C
Dec 1251C
Jan 1302C

6.50 mm .256 " 1/4

Nov 2047B
Dec 1151B
Jan 1202B

7.00 mm .276 " 9/32

Nov 1947A
Dec 1051A
Jan 802A

7.50 mm .297 " 19/64

Nov 1846E
Dec 950E
Jan 701E

8.00 mm .315 " 5/16

Nov 1746D
Dec 850D
Jan 601D

8.30 mm .328 " 21/64

Nov 1346F

8.50 mm .335 " 11/32

Nov 1346C
Dec 850C
Jan 501C

9.00 mm .354 " 23/64

Nov 1346B
Dec 750B
Jan 501B

9.50 mm .374 " 3/8

Nov 1246A
Dec 550A
Jan 401A

10.00 mm .394 " 25/64

Nov 1245J
Dec 549J
Dec 2353J
Feb 204J

10.30 mm .406 " 13/32

Nov 1145I
Dec 449I
Dec 2353I
Feb 204I

10.50 mm .414 " 13/32

Nov 1145H
Dec 449H
Dec 2353H
Feb 104H

11.00 mm .433 " 7/16

Nov 445G
Dec 449G
Dec 2253G
Jan 3004G

11.50 mm .453 " 29/64

Nov 1045F
Dec 349F
Dec 2253F
Jan 3004F

12.00 mm .472 " 15/32

Nov 1045E
Dec 349E
Dec 2253E
Jan 2904E

12.50 mm .493 " 31/64

Nov 645C
Dec 249C
Dec 1953C
Jan 2804C

13.00 mm .512 " 33/64

Nov 745D
Dec 349D
Dec 2153D
Jan 2904D

13.50 mm .531 " 17/32

Nov 545B
Dec 149B
Dec 1853B
Jan 2704B

14.30 mm .562 " 9/16

Nov 545A
Dec 149A
Dec 1853A
Jan 2704A

14.70 mm .578 " 37/64

Oct 2844H
Dec 148H
Dec 1852G
Jan 2603M

15.00 mm .593 " 19/32

Nov 344G
Dec 148G
Dec 1852F
Jan 2603L

15.90 mm .625 " 5/8

Nov 344F
Dec 148F
Dec 1752E
Jan 2503K

16.50 mm .650 " 21/32

Oct 3044A
Nov 2748A
Dec 1652A
Jan 1603A

17.50 mm .689 " 11/16

Oct 2944E
Dec 148E
Dec 1752D
Jan 2303J

18.25 mm .718 " 23/32

Oct 2944D
Nov 3048D
Dec 1752C
Jan 2303I

19.50 mm .768 " 49/64

Oct 3144C
Nov 2748B
Dec 1652B
Jan 1903B

20.25 mm .797 " 51/64

Oct 3044B
Nov 2748C
Jan 1903C

21.00 mm .828 " 53/64

Nov 3048Q
Jan 2203H

21.50 mm .844 " 27/32

Nov 244L
Nov 2848R
Jan 2203G

23.00 mm .906 " 29/32

Oct 3144J
Nov 2848P
Jan 2203F

23.80 mm .937 " 15/16

Oct 3144K
Nov 2848N
Jan 2003E

24.2 mm .953 " 61/64

Dec 1652H

25.5 mm 1.00 " 1/1

Nov 2748M
Jan 2003D