IRM ROLLING SCHEDULE

Rolling Schedule

Rolling dates are approximate and indicate the planned end of rolling. Delivery could be up to two weeks after the actual rolling.

  • 4.75 mm requires minimum of 350 tons to justify rolling.
  • Rebar requires minimum of 600 tons to justify rolling
  • All other diameters require minimum of 280 tons.

4.75 mm .1875 " 3/16

Dec 1461E
Jan 2002E
Feb 1806E

5.50 mm .216 " 7/32

Dec 1361C
Jan 1802D
Feb 1706D

6.00 mm .234 " 15/64

Dec 1261D
Jan 1602C
Feb 1306C

6.50 mm .256 " 1/4

Dec 1061B
Jan 1502B
Feb 1206B

7.00 mm .276 " 9/32

Dec 961A
Jan 1102A
Feb 1006A

7.50 mm .297 " 19/64

Dec 760E
Jan 1001F
Feb 705E

8.00 mm .315 " 5/16

Dec 660D
Jan 801E
Feb 605D

8.30 mm .328 " 21/64

Jan 801D

8.50 mm .335 " 11/32

Dec 660C
Jan 701C
Feb 605C

9.00 mm .354 " 23/64

Dec 660B
Jan 701B
Feb 505B

9.50 mm .374 " 3/8

Dec 560A
Jan 601A
Feb 405A

10.00 mm .394 " 25/64

Dec 559J
Feb 404J
Mar 408J

10.30 mm .406 " 13/32

Dec 459I
Feb 104I
Mar 308I

10.50 mm .414 " 13/32

Dec 459H
Feb 104H
Mar 308H

11.00 mm .433 " 7/16

Jan 3104G
Mar 208G

11.50 mm .453 " 29/64

Jan 3104F
Feb 2908F

12.00 mm .472 " 15/32

Jan 3004E
Feb 2908E

12.50 mm .493 " 31/64

Jan 2904C
Feb 2708C

13.00 mm .512 " 33/64

Jan 3004D
Feb 2808D

13.50 mm .531 " 17/32

Jan 2804B
Feb 2708B

14.30 mm .562 " 9/16

Dec 1462E
Jan 2704A
Feb 2608A

14.70 mm .578 " 37/64

Jan 2503G
Feb 2607L

15.00 mm .593 " 19/32

Jan 2403F
Feb 2607K

15.90 mm .625 " 5/8

Dec 1462D
Jan 2403E
Feb 2507J

16.50 mm .650 " 21/32

Dec 1462C
Jan 2103A
Feb 1907A

17.50 mm .689 " 11/16

Dec 1462F
Jan 2303D
Feb 2507I

18.25 mm .718 " 23/32

Jan 2303C
Feb 2407H

19.50 mm .768 " 49/64

Jan 2203B
Feb 1907B

20.25 mm .797 " 51/64

Jan 2203H

21.00 mm .828 " 53/64

Jan 2203I
Feb 2207F

21.50 mm .844 " 27/32

Feb 2207G

23.00 mm .906 " 29/32

Dec 1462B
Feb 2107E

23.80 mm .937 " 15/16

Dec 1462A
Feb 2007D

25.5 mm 1.00 " 1/1

Feb 2007C