IRM ROLLING SCHEDULE

Rolling Schedule

Rolling dates are approximate and indicate the planned end of rolling. Delivery could be up to two weeks after the actual rolling.

  • 4.75 mm requires minimum of 350 tons to justify rolling.
  • Rebar requires minimum of 600 tons to justify rolling
  • All other diameters require minimum of 280 tons.

4.75 mm .1875 " 3/16

Apr 1617E
May 1622E
Jun 1527E
Jul 1432E
Aug 1337E

5.50 mm .216 " 7/32

Apr 1517D
Apr 3020C
May 1522D
May 2424C
Jun 1427D
Jun 2330C
Jul 1332D
Jul 2534C
Aug 1337D
Aug 2940C

6.00 mm .234 " 15/64

Apr 2920B
May 1122C
May 2324B
Jun 927C
Jun 2230B
Jul 1132C
Jul 2334B
Aug 1037C
Aug 2740B

6.50 mm .256 " 1/4

Apr 2920A
May 1022B
May 2324A
Jun 827B
Jun 2130A
Jul 932B
Jul 2134A
Aug 1037B
Aug 2640A

7.00 mm .276 " 9/32

May 822A
Jun 627A
Jul 832A
Aug 937A

7.50 mm .297 " 19/64

May 621F
Jun 526E
Jul 631E
Aug 736E

8.00 mm .315 " 5/16

May 521E
Jun 326D
Jul 531D
Aug 636D

8.30 mm .328 " 21/64

May 321D
Jul 331F

8.50 mm .335 " 11/32

May 321C
Jun 226C
Jul 331C
Aug 436C

9.00 mm .354 " 23/64

May 121B
Jun 126B
Jul 331B
Aug 336B

9.50 mm .374 " 3/8

Apr 3021A
Jun 126A
Jul 231A
Aug 236A
Aug 3041A

10.00 mm .394 " 25/64

Apr 2919J
May 3125J
Jun 3029J
Aug 135J
Aug 2539J

10.30 mm .406 " 13/32

Apr 2819I
May 3025I
Jun 2929I
Jul 3135I
Aug 2439I

10.50 mm .414 " 13/32

Apr 2819H
May 3025H
Jun 2929H
Jul 3135H
Aug 2439H

11.00 mm .433 " 7/16

Apr 2719G
May 2925G
Jun 2829G
Jul 3035G
Aug 2339G

11.30 mm .445 " #10M

Apr 2118S
May 2223S
Jun 2128S
Jul 1933S
Aug 1838S

11.50 mm .453 " 29/64

Apr 2619F
May 2925F
Jun 2729F
Jul 2935F
Aug 2239F

12.00 mm .472 " 15/32

Apr 2419E
May 2825E
Jun 2729E
Jul 2935E
Aug 2239E

12.50 mm .493 " 31/64

Apr 2219C
May 2625C
Jun 2529C
Jul 2735C
Aug 2039C

13.00 mm .512 " 33/64

Apr 2319D
May 2725D
Jun 2629D
Jul 2835D
Aug 2139D

13.50 mm .531 " 17/32

Apr 2219B
May 2525B
Jun 2429B
Jul 2635B
Aug 1939B

14.30 mm .562 " 9/16

Apr 2119A
May 2525A
Jun 2429A
Jul 2635A
Aug 1839A

14.70 mm .578 " 37/64

Apr 2018G
May 2223M
Jun 2028G
Jul 2033L
Aug 1738G

15.00 mm .593 " 19/32

Apr 2018F
May 2123L
Jun 2028F
Jul 2033K
Aug 1638F

15.90 mm .625 " 5/8

Apr 1918E
May 2123K
Jun 1928E
Jul 2033J
Aug 1638E

16.10 mm .629 " #15M

Apr 2118R
May 2223R
Jun 2128R
Jul 1933R
Aug 1738R

16.50 mm .650 " 21/32

Apr 1718A
May 1723A
Jun 1628A
Jul 1433A
Aug 1438A

17.50 mm .689 " 11/16

Apr 1918D
May 2123J
Jun 1928D
Jul 1833I
Aug 1638D

18.25 mm .718 " 23/32

Apr 1918C
May 2023I
Jun 1928C
Jul 1833H
Aug 1538C

19.50 mm .768 " 49/64

Apr 1818B
May 1723B
Jun 1628B
Jul 1533B
Aug 1538B

20.25 mm .797 " 51/64

May 1823C
Jun 1628M
Jul 1633C

21.00 mm .828 " 53/64

May 1923G
Jun 1828N
Jul 1833G

21.50 mm .844 " 27/32

May 2023H
Jul 1733F

23.00 mm .906 " 29/32

May 1923F
Jun 1828L
Jul 1733E

23.80 mm .937 " 15/16

May 1923E
Jul 1633D

24.2 mm .953 " 61/64

May 1818K

25.5 mm 1.00 " 1/1

May 1823D
Jun 1728K