IRM ROLLING SCHEDULE

Rolling Schedule

Rolling dates are approximate and indicate the planned end of rolling. Delivery could be up to two weeks after the actual rolling.

  • 4.75 mm requires minimum of 350 tons to justify rolling.
  • Rebar requires minimum of 600 tons to justify rolling
  • All other diameters require minimum of 280 tons.

4.75 mm .1875 " 3/16

Oct 2840K
Nov 2445J

5.50 mm .216 " 7/32

Oct 2740J
Nov 643C
Nov 2345I
Dec 947C

6.00 mm .234 " 15/64

Oct 2640I
Nov 543B
Nov 2245H
Dec 747B

6.50 mm .256 " 1/4

Oct 2640H
Nov 443A
Nov 2145G
Dec 547A

7.00 mm .276 " 9/32

Oct 2540G
Nov 2145F
Dec 1550A

7.50 mm .297 " 19/64

Oct 2340F
Nov 2045E
Dec 1449F

8.00 mm .315 " 5/16

Oct 2140E
Nov 1845D
Dec 1449E

8.30 mm .328 " 21/64

Oct 2040D
Dec 1349D

8.50 mm .335 " 11/32

Oct 2040C
Nov 1745C
Dec 1349C

9.00 mm .354 " 23/64

Oct 1940B
Nov 1645B
Dec 1249B

9.50 mm .374 " 3/8

Oct 1840A
Nov 1545A
Dec 1249A

10.00 mm .394 " 25/64

Nov 1344J
Dec 1148I

10.30 mm .406 " 13/32

Nov 1244I

10.50 mm .414 " 13/32

Nov 1244H
Dec 1148H

11.00 mm .433 " 7/16

Nov 1144G
Dec 1148G

11.30 mm .445 " #10M

Nov 1444L

11.50 mm .453 " 29/64

Nov 1144F
Dec 1048F

12.00 mm .472 " 15/32

Nov 1044E
Dec 1048E

12.50 mm .493 " 31/64

Nov 844C
Dec 1048C

13.00 mm .512 " 33/64

Nov 944D
Dec 1048D

13.50 mm .531 " 17/32

Nov 744B
Dec 948B

14.30 mm .562 " 9/16

Nov 644A
Dec 948A

14.70 mm .578 " 37/64

Nov 342M
Dec 446K

15.00 mm .593 " 19/32

Nov 342L
Dec 446J

15.90 mm .625 " 5/8

Nov 242K
Dec 446I

16.10 mm .629 " #15M

Nov 1444K

16.50 mm .650 " 21/32

Oct 2941A
Nov 2546A

17.50 mm .689 " 11/16

Nov 242J
Dec 446H

18.25 mm .718 " 23/32

Nov 142I
Dec 446G

19.50 mm .768 " 49/64

Oct 3041C
Dec 246B

20.25 mm .797 " 51/64

Oct 2941B

21.00 mm .828 " 53/64

Nov 142G

21.50 mm .844 " 27/32

Nov 142H
Dec 346F

23.00 mm .906 " 29/32

Oct 1637E
Oct 3142F
Dec 346E

23.80 mm .937 " 15/16

Oct 1737D
Oct 3142E
Dec 346D

24.2 mm .953 " 61/64

Dec 246L

25.5 mm 1.00 " 1/1

Oct 3041D
Dec 246C