IRM ROLLING SCHEDULE

Rolling Schedule

Rolling dates are approximate and indicate the planned end of rolling. Delivery could be up to two weeks after the actual rolling.

  • 4.75 mm requires minimum of 350 tons to justify rolling.
  • Rebar requires minimum of 600 tons to justify rolling
  • All other diameters require minimum of 280 tons.

4.75 mm .1875 " 3/16

Dec 154E
Jan 359E
Feb 105E
Mar 110E
Apr 115E

5.50 mm .216 " 7/32

Nov 2954D
Dec 1056C
Dec 2359D
Jan 1903C
Feb 105D
Feb 1307C
Mar 110D
Mar 1913C
Apr 115D

6.00 mm .234 " 15/64

Nov 2053M
Nov 2554C
Dec 856B
Dec 2259C
Jan 1403B
Jan 2805C
Feb 1107B
Feb 2510C
Mar 1613B
Mar 2915C

6.50 mm .256 " 1/4

Nov 2454B
Dec 756A
Dec 2159B
Jan 1403A
Jan 2705B
Feb 1007A
Feb 2510B
Mar 1613A
Mar 2915B

7.00 mm .276 " 9/32

Nov 2354A
Dec 2059A
Jan 2605A
Feb 2310A
Mar 2815A

7.50 mm .297 " 19/64

Nov 2253F
Dec 2058E
Jan 2504F
Feb 2209E
Mar 2614F

8.00 mm .315 " 5/16

Nov 2253E
Dec 1858D
Jan 2404E
Feb 2109D
Mar 2514E

8.30 mm .328 " 21/64

Nov 2053D
Jan 2204D
Mar 2414D

8.50 mm .335 " 11/32

Nov 2053C
Dec 1758C
Jan 2104C
Feb 1909C
Mar 2314C

9.00 mm .354 " 23/64

Dec 1758B
Jan 2004B
Feb 1809B
Mar 2214B

9.50 mm .374 " 3/8

Dec 1658A
Jan 2004A
Feb 1809A
Mar 2214A

10.00 mm .394 " 25/64

Nov 2253Q
Dec 1657J
Jan 1202J
Feb 1708J
Mar 1412J

10.30 mm .406 " 13/32

Dec 1657I
Jan 1202I
Feb 1708I
Mar 1212I

10.50 mm .414 " 13/32

Dec 1557H
Jan 1102H
Feb 1608H
Mar 1112H

11.00 mm .433 " 7/16

Dec 1557G
Jan 1102G
Feb 1608G
Mar 1112G

11.50 mm .453 " 29/64

Dec 1357F
Jan 1102F
Feb 1608F
Mar 1012K

12.00 mm .472 " 15/32

Dec 1357E
Jan 1002E
Feb 1508E
Mar 1012E

12.50 mm .493 " 31/64

Dec 1257C
Jan 902C
Feb 1408C
Mar 912C

13.00 mm .512 " 33/64

Dec 1357D
Jan 1002D
Feb 1508D
Mar 1012D

13.50 mm .531 " 17/32

Dec 1157B
Jan 702B
Feb 1408B
Mar 812B

14.30 mm .562 " 9/16

Dec 1157A
Jan 702A
Feb 1408A
Mar 812A

14.70 mm .578 " 37/64

Dec 455M
Jan 601G
Feb 906M
Mar 611G

15.00 mm .593 " 19/32

Dec 455L
Jan 601F
Feb 806L
Mar 611F

15.50 mm .609 " 39/64

Dec 356M
Jan 601M
Feb 806R

15.90 mm .625 " 5/8

Dec 355K
Jan 601E
Feb 806K
Mar 511E

16.50 mm .650 " 21/32

Dec 155A
Jan 401A
Feb 206A
Mar 211A

17.50 mm .689 " 11/16

Dec 355J
Jan 501D
Feb 706J
Mar 511D

18.25 mm .718 " 23/32

Dec 355I
Jan 501C
Feb 706I
Mar 411C

19.50 mm .768 " 49/64

Dec 155B
Jan 501B
Feb 306B
Mar 311B

20.25 mm .797 " 51/64

Dec 255C
Feb 306C

21.00 mm .828 " 53/64

Dec 255G
Feb 606G

21.50 mm .844 " 27/32

Dec 355H
Feb 706H

23.00 mm .906 " 29/32

Dec 255F
Feb 506F

23.80 mm .937 " 15/16

Dec 255E
Feb 506E

25.5 mm 1.00 " 1/1

Dec 255D
Feb 406P